Friday, August 10, 2018

Register Sealing before having BECT do a duct leakage test


Subject : Register Sealing before having BECT do a duct leakage test

Hello,
Please make sure that the registers are sealed as in the photo below, before BECT comes to test the system for duct leakage.
Seal the register boxes to drywall or hardwood floor with UL 181 aluminum tape as shown below.

Aluminum Tape (must be UL 181)        

                              Register sealed to drywall with Al tape.


The photos below are examples of what the registers/returns should not look like.
Unsealed boot in drywall, on ceiling. This won't hold air.





Unsealed 1950s boot in hardwood floor, unsealed.




1920s register boot, unsealed to plaster yet painted black.

Also, please make sure that your forced air unit set on the highest speed so that you can achieve 350 cfm/ton​ for the 1. Total Airflow Test and 2. The Fan/Watt Draw Test.


Also, don't forget to drill a 1/4 inch hole in each side of the plenum (both supply plenum and return plenum) and mark the hole, HSSP, for Hole for Static Pressure Probe. Put aluminum tape over the hole but make sure marking is visible for HERS test. If those access holes are not there - you'll need to do it at the test. They are so that someone can insert a probe on each side and see the difference in temperature and humidity changes before and after the air moves through the evaporator coil.

If you have any questions on how to seal it, we also have a video on our website detailing how to properly seal your ducts. Click this link here to watch the video, http://bect.us/videos/. You can also watch our other videos on energy efficiency in the home on BECT's YouTube channel. Check it out here, https://www.youtube.com/channel/UCAd8LCb6fzHAkzqOu9loGrQ/videos?view_as=subscriber.



Stay cool and comfortable, 


BECT

Tuesday, October 31, 2017

"Like Italy in the 1960s", HVAC contractors have no idea how to build to California's Energy Code.


A lovely guest house in the country. Brand new, white, gleaming and beautiful. The owner is British. I tested the performance of her new HVAC system. It failed three HERS tests.

I explained to her each of the tests and why the system failed. The ducts leaked too much air. The system did not move enough air for the size of the air conditioner. Why? The return ducts are either too few or too small. The MERV 8 filter installed is restricting air flow so it should be bigger or perhaps there should be two of them. The 2017, airtight, well insulated 1500 square foot house with low e, argon dual pane windows doesn't take much to heat or cool. How did it end up with a 3 ton AC and restricted, leaky ducts?

The homeowner told me that it was "like Italy in the 1960s." A top-heavy bureaucracy well insulated from those doing the actual work or needing to get things done. The individual people are often brilliant, but people are not working together. Some were also incompetent.

We have a real problem in the SF Bay area with HVAC contractors installing air conditioning systems without following the CA energy code's "Mandatory Measures", nor CalGreen. Every day I test new systems that have not been sized and designed as per code requirements. This yields systems that use more energy and provide less comfort. This has a real effect on energy use in the SF Bay Area. These improperly designed system can last 30 years or more and will waste energy daily 'til near 2050 when they will fail.

California Title 24 Energy experts say that 1% of residential HVAC systems are properly calculated for sizing and have their ducts designed per the specs in Title 24. Only 10% get permitted and tested.

Of course, the Energy Commission did not make up these design specs. They use the Air Conditioner Contractor's of America Manual J, Manual D and Manual S sizing, duct and register grill design specifications.

Sadly, there is no continuing education from the Contractors State License Board for HVAC contractors. Hence, they have no idea of what is in the California Energy Code or how to build comfort system that conform to it.

We are now in the 2016 energy code. Builders and HVAC contractors are nowhere near understanding what is in the current code or how to meet it. At the same time we are nearly 2 years away from the 2020 energy code when new buildings will be "Zero Net Energy", meaning that houses will generate as much energy in a year as they use in a year. We have a lot of work to do to educate the building industry workforce in order to get up to speed with upcoming code changes.

Let's fix this problem.  Just like engineers design our building so they stand up to earthquakes via code required structural design, let's have our HVAC systems engineered per our energy code. We need to require building department design review first, before permitting these long lasting, energy using systems to get built.

CSLB and California local Building Departments, please get up to speed educating the building industry workforce and enforcing the energy code.

George Matthews, owner
Building Energy Compliance Testing
Serving the San Francisco Bay Area

Thursday, May 4, 2017

Failed HERS Test and Final Inspection - How to Avoid the Pain and Expense and a Solution to the Problem



It happened again, yesterday, doing a HERS test on a new house, HERS testing the air conditioning system.
This was the third time I was at this house testing. The technician, not an HVAC contractor but a tech hired by the owner, had added another duct to coax the 5 ton air conditioner into blowing 1750 cubic feet of air per minute, the minimum required by code.

The system did not perform to code. It moved 1600 CFM but not the 1750 required by the State of California. We looked at his work. He'd added a shiny silver drooping limp flex duct connected to a small return filter box. He told me there was nothing more he could do. I suggested pulling it taught in a straight line to the return. He didn't think that would work. He really did not like my alt suggestion of a straight metal duct to reduce air friction.

I exited the front door with him. He threw is boots hard at the driveway and cursed in anger. I could sense deep frustration and a man who probably won't get paid until the job passes. I felt sorry for him. He did not know that these systems are supposed to be sized according to manual J, Manual D and Manual S in software such as Wrightsoft. The owner or builder had signed off on building to the Calgreen checklist which states that the HVAC system will be sized according to Manual J, D and S. Apparently, no one took that seriously. The City of Orinda building department never asked for this basic engineering. Hence, it never got done.

The technician had guessed the system together. The 2600 square foot house in mild, often foggy Orinda, California somehow received a 5 ton air conditioner, the largest available. When it failed he asked me what to do. I had to tell him that I am not the designer but the State's Energy Commission does have something called the Building HVAC Requirements.  http://www.energy.ca.gov/2013publications/CEC-400-2013-001/chapters/04_Building_HVAC_Requirements.pdf

In these Building HVAC Requirements, under table 4-11 (Standards Table 150-D): Return Duct Sizing for Multiple Return Duct Systems, there is a line that shows a 5 ton air conditioning duct system having two 20 inch return ducts with a minimum gross filter grill face area of 1500 square inches.

The system I was testing did not have anywhere near 1500 square inches of filter grill face. It had two filters equaling 768 square inches, about half what code is requiring.

If this system had actually been designed rather than guessed together by a person using some "rules of thumb", it most probably would have passed the first time. The problem is that this is the 3rd time I've seen this in a ten days. It happens all the time in the affluent, well educated San Francisco bay area, home to so much energy efficiency research and development.

I usually ask air conditioner contractors how they sized the system I'm about to test. Almost invariably they tell me they use the "square footage rule". "What is that?" I ask. They then explain that for every 500 square feet of house they put in a ton of AC. Easy! 2500 square feet of house equals 5 tons of AC. System sizing complete! Sometimes they admit that the guy at the supply house told them what size was needed.

We know the problem. HVAC contractors and unlicensed technicians who install HVAC systems don't size those systems according to protocol of the Air Conditioning Contractors of America. The results are brand new, shiny yet poorly operating systems that will waste energy and perform poorly for decades to come.

Here's the solution. City Building Departments must get manual J, D and S designs before contractors can build that system. Just as seismic engineering is required for buildings before they are built, so to can we require that mechanical systems be engineered before they are built. Then we just have to work with the problem that the residential HVAC industry evades building departments permits and code HERS testing some 90% of the time.

Friday, November 6, 2015

Duct Testing in the San Francisco Bay Area

As a HERS rater I travel all over the San Francisco Bay Area and test HVAC systems for code compliance.

What I so often see is systems that just barely scrape past the code requirements or are over and need more work to get them to pass the duct test. Recently I learned about a club of HVAC contractors who actually pass the test so well that the test equipment can’t even read how much air is leaking from their systems. That is because there is almost no air leaking from their ducts, fittings and air handler units. How do they get these contractors get their systems to be so air-tight?

To begin, there are only eight HVAC  contractors in California who are building HVAC duct systems so tight as to earn their way to the “4 Ring Club”. Ring 4 refers to the Energy Conservatory duct leakage test system’s #4 ring which is the smallest. It is the one used on the smallest and most leak-free systems. These installers build ducts that even Ring 4 can’t register. These elite contractors can be found at http://ring4club.com/. They are all Home Performance contractors, a title that discerns them from standard HVAC contractors. They install high performance comfort systems. They are the hot rodders of the HVAC world.

What do they do differently? One, they see the house as a system and create larger work scopes than standard HVAC contractors. They start at the shell of the building and do a home energy retrofit rather than just  “changing out the box” or replacing an old furnace or air conditioner with a new, usually same sized unit. These techs do it by the book. They do a manual J heat load calculation, manual D duct design and a Manual T register design to dial in performance to every part of their HVAC system.

When it comes to installations, what they do differently is to actually commission their work. This means that after the work is done, and even during installation, they test every performance aspect of their work.


Regarding ducts, they paint every piece of metal duct connections and any part of metal to metal with a thick application of air duct mastic. Secondly, they properly clamp the flex ducts onto the sheet metal. Here, properly means that instead of hand tightening the zip-ties over the connection, they use a tensioning tool such as http://www.homedepot.com/p/Malco-Manual-Cut-Off-Tensioning-Tool-with-Grips-TY4GTS/100161814.  A recent Home Energy Magazine article notes that the difference between hand tensioning and using a tensioning tool is significant air loss. Lessen: use a tensioner for tight ducts.

Thursday, October 29, 2015

HERS RATINGS, DUCT TESTS AND PERFORMANCE DESIGN: ACHIEVING COMFORTABLE, LOW ENERGY USE HOMES AND ACTUAL ENERGY EFFICIENCY

As a HERS Rater who tests duct systems all over the San Francisco bay area and the Silicon Valley, I confront system failure all too often. Every day I see brand new heating and air conditioning systems that are woefully sub-optimized and fail to comply with California’s 2013 energy code. When those systems finally do pass they are usually skating just under the legal limit of duct leakage and air flow for air conditioning.

Yesterday I attended a PG&E sponsored energy efficiency class, Optimizing Residential HVAC System Performance. The class reminded me just how much that we, as an industry, know about HVAC systems, their optimization and have the ability to build, if we care enough to do so. The presentation showed a group of HVAC contractors who build their duct systems so air-tight that the lowest setting on their test equipment shows  “error”.  These contractors take delight in the fact that almost no other contractors can match their specs when it comes to air tightness. At this performance level, there is almost no competition.

Other highlights of the class, the instructor showing how he took an 18,000/40,000 btu per hour furnace and disconnected the high end.  The reason he could do that was because he actually did the load calculations and knew just how much heating and cooling the house needed and provided just that. He actually designed the return system so that it did not constrict airflow and complied with the 2013 California code. He made the duct system as short and low resistance as he could and then built air registers that were designed to throw the air at the far walls with engineered grills. After completion, he commissioned the system and did a room by room airflow test and balanced the system.  Wow!  

It was such a change from what I usually encounter that it seemed like a different industry. In the field I see contractors struggle to get 350 cfm per ton of air conditioning. In the class, the instructor noted that California’s dry climate allows us to shoot for much higher airflows per ton such as 500, 600 or more cfm per ton. To do this one must learn how to hot rod the air handler. It is do-able, and it provides more energy efficiency and comfort per energy dollar spent. The longer run times provide better filtration and heat the house more evenly than an oversized system.

One class technique was really interesting in terms of comfort provided. The instructor noted that he designed his heating system to blow air around 82 degrees F rather than 120 F. This, and the longer run times provides room air temperatures that are within a few degrees from floor to ceiling. Hot air stratifies in a room, warm air, not so much.  Again, this gives him a market edge, he can guarantee that there is only a 2 degree difference from floor to ceiling; market advantage. His competitors can’t match this.

In a few seconds I can usually get a good idea if an HVAC system is going to be code level air-tight. If I see mastic on all the connections, I can be nearly assured that the system is going to pass without my helping to troubleshoot the leaks in the system. In my experience, people just don’t realize how thin and slippery air is. I’ll ask, “Did you use mastic?.” I’ll often get answers like “What’s that?” or “Oh that stuff… it’s really messy.” Then they go back up into a hot attic and try to and find the leaks. This is rarely a good experience. Doing it right the first time is a better strategy for profitability.

We have a lot of tools at hand to help us build better HVAC systems and would benefit us, as an industry, to use them. The first is the energy code, anything below which, is illegal. The first thing one should do is to read the California 2013 Residential Compliance Manual. Another tool is the ability to do load calculations and duct design software such as Wrightsoft . My field experience shows me that load calcs are all-too-often crude guesses. This fixes that problem.

HVAC optimization is thus, measure a building’s actual need for heating and cooling with load calculations. Specify efficient equipment that matches load calcs. Actually design a compact, low restriction duct system. Install the system so that it does not leak any measurable about of air. Install register grills that puts the right amount of air where it is needs to go at the right speed. Commission the system by measuring and balancing room by room duct air flow, duct leakage and total airflow at the return.  

We have the ability to build highly energy efficiency comfort systems if we use the tool s at hand. Using tools such as utility sponsored trainings, understanding code requirement and using available software design are the way to get there. Doing so can make a contractor more desirable to customers and hence profitable. It can also give one the existential pleasure of doing something well. Building an HVAC installation industry that does its job well can be a powerful tool toward building an energy efficient economy and low carbon future.

George Matthews
Building Energy Compliance Testing
San Francisco/Silicon Valley

www.bect.us

Wednesday, October 7, 2015



common energy mistakes of builders,  home owners and Code Officals
Or, Confessions of a frustrated Home Performance professional

Missing or insufficient insulation.
Most every day I see under-insulated and sometimes completely uninsulated attics. It is so easy and effective to insulate them and the benefits of comfort and energy savings are so great.  Today I did a pre-solar inspection on a house from 1965. The attic had zero insulation. One would think that before the most advanced energy measure, solar electric generation, that one would do the type of energy measure that was done as a code requirement in 1970. However there is no trigger to make this happen.
I recently tested a house on the peninsula. It had just undergone a $700,000 remodel to make it a mansion for a tech executive with a taste for Mediterranean style. It was going for sale for 2 or 3  million dollars.  It was perfect. Except for the attic insulation. It had gaping holes in it and was more of a 1980s job than one fitting the 2013 California Energy Code. There was nothing I could do about it. No trigger.

Leaky hatch to attic.
This is extremely common. What is highly uncommon is to see a properly weatherstripped attic access hatch door that is insulated. This is essentially a 5 square foot energy hole in most every ceiling in California.

No radiant barrier on reroof or addition of ply to roof.
I experience hot attics all the time.  They don’t have to be that way.  When reroofing it is easy to add Kool-Ply rather than old fashioned plywood or OSB. It costs about 10 cents per square foot to upgrade to the radiant barrier covered plywood.
Back in the early 90’s it was common knowledge in energy circles that radiant barriers really worked. Carpenters on the job could tell the difference there under a roof with a radiant barrier from one without. It was pleasant under the radiant barrier and hot under old fashioned plywood.
In some areas a radiant barrier in the attic could be the difference between needing air conditioning or not. Please specify Kool-Ply on your next reroofing job, new house or addition.

No insulation on raised floors in houses with crawlspaces or basements.
You don’t have to have cold feet all winter long and waste energy. You can really feel it. I insulated the floor of an old house. The tenant called me up to thank me. I did not tell him about the insulation, he felt it. I remember being told by PG&E people back in the 80’s that floor insulation was not cost effective. Don’t believe it. 
Insulation is not very expensive, it has no moving parts and will last til it gets infested with rats or gets wet. Rodent proof your crawlspace to keep rodents and their feces out of house. (Some 60% of air inside a house originates from crawlspaces.) Protect the air you and your family breathe. Get your floor properly insulated after you rat proof it. You'll have happier feet and no mice.

A brand-new 1970s era furnace!
Your HVAC installer just sold you a 1970s era furnace in late 2015. This is in the state with the strictest energy code in the nation, the one leading the way in cutting carbon and fighting climate change.
I see this every week.  Even though we’ve been replacing these old units for decades, sometimes with detailed energy savings calculations, contractors still sell people these inefficient units because they have a low first cost. We know that the costs we should be concerned with are the lifetime costs of heating system because that is the larger and more significant cost. Spend a few hundred dollars more for a level of efficiency and safety more 2015 than 1979.

Combustion Safety
I just had to pay $500 more for insurance because I do “BPI” work. BPI is the Building Performance Institute, a non-profit organization that teaches and certifies contractors how to test houses for carbon monoxide, gas leaks and energy efficiency. (They do more really. Check out BPI.org).  That means that I do the tests of houses with old-style open-combustion gas appliances. If the houses that these appliances are in ever get a strong enough negative pressure in them, combustion gasses can escape inside and sicken or kill the people who live there.  This is why we should not sell these units anymore. Buy the cheapest 90% efficiency furnace, one that is sealed-combustion rather than an old-style open combustion unit.

Not getting a furnace or air conditioner tested by a HERS Raters.
The HERS energy testing industry in California speculates that some 85 or 90 percent of comfort systems are not tested by a third party inspector after installation. Nobody really knows the real answer.  If the California Energy Commission does know, they are not letting on about it. However, in California, code requires third party HERS duct leakage and air conditioner testing.

 Do these undocumented systems perform to the manufacturer’s, Federal and state government’s energy code specifications? Does it blow the right amount of air? How much does the duct system leak? Does the air actually go where it is supposed to? Is there a gas leak? Will it help California’s buildings become 50% more energy efficient by 2030 to comply with Senate Bill 350? We’ll never know the answers, because it didn’t get tested.

Oversized air conditioning and heating systems.
Every day I see HVAC contractors install furnaces just as they have been doing their entire careers. They put in a 66,000, 80,000 or 100,000 btu per hour furnace in a house that might need a 40,000 btu per hour unit. The same thing happens with air conditioners which use far more electricity. There are some perverse yet strangely logical reasons why contractors do this. I won’t get into that.

Why are these systems oversized and wrong-sized? Because installers use simple and incorrect “rules of thumb” rather than doing the math like professionals.  Of course, the energy code in California requires that HVAC system be sized according to the ACCA . This means that the HVAC contractor is required to use software such as WrightSoft and input the building plans into the program including volume, windows, wall assemblies, insulation and orientation.

This is what I see in my work. Of course, as noted above, as a HERS Rater I only see the 5 or 10 percent of work by contractors who actually have contractors’ licenses and get their work inspected. What about the other 90 percent? I can only guess that with no one in back of them testing their work, demanding that they do it right, that it is probably less-than-code compliant work. Even those contractors doing everything right mostly just scrape by passing code by a thin margin.

I suspect that if the California Contractors State License Board and City and County Building Departments actually clamped down and forced code compliance, and the requirements that HVAC installers obtain a contractor’s license, get building permits and get their work tested, that energy use would go down and California citizens; energy consumers and carbon emitters, would have systems that work properly and provided more comfort, energy savings and climate mitigation.

Every HVAC system uses natural gas, electricity and creates combustion gasses. Each of these can kill you. It makes sense to follow the building code and energy code and inspect and these systems that are found in every California house.

George Matthews
Building Energy Compliance Testing
San Francisco to Silicon Valley